Chrysler Canada Trucks (Build Out Start Up)

Last Updated: 9/15/20
Bold indicates latest update. Letter after date corresponds to main category.

MODEL DODGE MODEL JEEP MODEL RAM 2020 INITIAL ORDERS ACCEPTANCE1  2020 PRODUCTION BEGINS1  2020 ORDERS DUE TO DONLEN1  2020 ORDERS DUE1  2021 INITIAL ORDERS ACCEPTANCE1  2021 PRODUCTION BEGINS1 
Durango 05/20/19 07/29/19 Completed4 Completed4 8/6/20 10/5/20
Grand Cherokee 06/24/19 07/29/19 Completed4 Completed4 7/8/20 9/14/20
Cherokee 06/24/19 07/22/19 Completed4 Completed4 6/12/20 8/31/20
Renegade 06/07/19 08/15/19 Completed4 Completed4 7/8/20 7/8/20
Wrangler 06/24/19 07/15/19 Completed4 Completed4 6/12/20 8/10/20
Compass 06/24/19 08/05/19 Completed4 Completed4 6/12/20 8/3/20
Ram 1500 Classic Reg Cab (DS) 11/29/192 1/2/20 ASAP2 2/14/202 9/15/20 11/23/20
Ram 1500 Classic Quad/Crew Cab (DS) 11/29/192 12/16/19 ASAP2 2/14/202  9/15/20 11/16/20
Ram 1500 Quad/Crew Cab (DT) 05/15/19 07/22/19 Completed4 Completed4 6/30/20 8/31/20
Ram 2500-3500 09/23/19 11/25/19 8/21/20 8/28/20 9/4/20 11/17/20
Ram 3500/4500/5500 Cab Chassis 11/8/19 11/25/19 8/21/20 8/28/20 9/4/20 11/17/20
Promaster City 06/3/19 07/01/19 5/22/203 5/22/203 6/12/20 Sept. 2020
ProMaster 06/24/19 09/30/19 4/3/20 4/10/20 6/12/20 8/24/20

1 – All dates are estimated and subject to change.

2- RAM 1500 CLASSIC (DS) Pickup at WTAP – With the exception of the models and configurations in the following schedule, all production requirements have now been covered. These remaining configurations have limited production available at WTAP through March:

Model Body Model CPOS Powertrain
Ram 1500 (DS) Express DS6L41 27J 5.7L Hemi
Ram 1500 (DS) Express DS6L98 26J/27J 5.7L Hemi
Ram 1500 (DS) SLT DS6H98 26G 5.7L Hemi
Ram 1500 (DS) Warlock DS6H98 27F 5.7L Hemi

Please note that all production requirements for all 3.6L Pentastar V6 models and configurations have been covered.
To secure the final supply of parts required to fulfill expected demand and to finalize the pre-shutdown production plan for the Ram 1500 Classic (DS), final order submissions will need to be submitted by February 14th (Communicated on FCA Canada on 2/10/20)

3- Cutoff dates communicated by FCA Canada on 5/21/20
4- Completed order dates communicated by FCA Canada on 6/19/20